Tuesday, August 17, 2010

Aug 16: Prep for Stem Wall Pour

These photos show the placement of rebar around the main cable truss post.  The stem wall forms jog around the post and rebar for good concrete coverage of the assembly. 



The following photos show details of the rebar assembly that will tie the base of the main cable truss into the concrete footing and stem wall for maximum strength for an important structural connection.

At the end of a hot day, which Todd said reached 100 deg F, tube steel posts stand braced, steel rebar is in place, and stem wall forms are up and baking in the high desert sun ready to receive the cool early morning pour of concrete.